Thursday, October 27, 2011

Maintenance Management - 11

Maintenance Management - 11


Select The Blank
Question Lubrication is said to be the ________ system of equipment.
Correct Answer Nervous


True/False
Question Reports are of no use if no action is taken on them to
correct the deficiencies.
Correct Answer True


Select The Blank
Question ________ are involved for moving of store items from store
to actual use place.
Correct Answer Handling expenses


True/False
Question Too may cooks spoil the broth.
Correct Answer True


Multiple Choice Multiple Answer
Question Evaluation of maintenance function can be done by taking
following steps :-
Correct Answer Set the achievable targets for maintenance dept for
the expected performance , Check results against set targets , Find out
reasons for variance


True/False
Question Operating information is all relevant data of system &
equipment.
Correct Answer False


Multiple Choice Single Answer
Question How a molecule of fuel fragmented?
Correct Answer H+ and OH-


True/False
Question The cost of the ordering can be also substantial in case of
large organizations.
Correct Answer True


Multiple Choice Single Answer
Question During commissioning of the equipment it is necessary to
train the staff & workers can be done with help of :-
Correct Answer Commissioning manuals & equipment supplier technical
team.


True/False
Question PERT is event oriented while CPM is activity oriented.
Correct Answer True


Multiple Choice Single Answer
Question Who is supposed to develop a clear-cut policy on line of
authority?
Correct Answer Maintenance manager


Multiple Choice Single Answer
Question Identify the method for coding "MA" :-
Correct Answer Mnemonics method


True/False
Question Experience shows that no matter how much money & time is
spent on preventive maintenance, the breakdown do occur.
Correct Answer True


Multiple Choice Single Answer
Question What is the requirement of effective & timely maintenance?
Correct Answer Organizational Support


Multiple Choice Multiple Answer
Question The objective inventory control is :-
Correct Answer To reduce lead time , To reduce finance cost of
inventory , To reduce storage cost of material


Multiple Choice Multiple Answer
Question What information is given in a manual of building?
Correct Answer Maintenance of building , Schedule of maintenance ,
Description of maintenance


Multiple Choice Multiple Answer
Question What are the factors on which electrical current severity
depends?
Correct Answer Time of passage of current , Magnitude of current ,
Path of current


Multiple Choice Multiple Answer
Question Which are the major hazards which can occur in Industry?
Correct Answer Toxicity , Radioactivity , Poisons


Multiple Choice Multiple Answer
Question Development of subordinates broadly will depend on :-
Correct Answer The level of education , The level of personal skill
, The level of intelligence


Multiple Choice Single Answer
Question On what basis success of inspection depends?
Correct Answer Dedication of Staff


Select The Blank
Question Quality should not be ________ at the cost of lower price.
Correct Answer Sacrificed


True/False
Question The steam trap plays a vital role in the performance of the
machine.
Correct Answer True


Multiple Choice Multiple Answer
Question The role of maintenance manager in New project is :-
Correct Answer To study of vendor assistance proposal , Study of
operating & maintenance requirement , To study monitoring technique


Select The Blank
Question There are two types of fault diagnostic charts, ________ &
dependency chart.
Correct Answer Algorithm


Multiple Choice Multiple Answer
Question Fire can be extinguished by?
Correct Answer Taking away heat , Stopping oxygen , Chemical
extinguishing


Multiple Choice Single Answer
Question Which Network Analysis is used for Time saving in
overhauling?
Correct Answer CPM


Select The Blank
Question The contract service is ________.
Correct Answer Too expensive


True/False
Question A proper man for proper job should be a natural choice.
Correct Answer True


Match The Following
Question- Correct Answer
Aging schedule -Fast & slow moving items
Ordering cost -Advertisement expenses
Stock out cost- Effect on worker moral
EOQ -Reorder level


Multiple Choice Single Answer
Question When to do inspection?
Correct Answer Running Condition


Multiple Choice Single Answer
Question Proper spare part will enhance the life of equipment and
will save vital :-
Correct Answer Capital expenditure


Select The Blank
Question ________ & maintenance department are closely interlinked to
each other.
Correct Answer Production


Multiple Choice Multiple Answer
Question Some of the elements of the ordering cost are :-
Correct Answer Cost of stationary used for purchase function ,
Depreciation for the furniture, computer & other equipments , Entertainment
of vendors.


True/False
Question Damage to the work in process material can be considered as
indirect cost of an accident.
Correct Answer True


Select The Blank
Question ________ is an invisible, yet important cost.
Correct Answer Stock out cost


Multiple Choice Multiple Answer
Question The following costs can be treated under the heads of Wages
and salaries :-
Correct Answer The salaries of foreman, fitters, electricians etc.
, Overtime charges. , Contract labor charges.

Select The Blank
Question If the job performed on the purchased equipment is OK in
terms of quality & quantity, which was conceived at the beginning is known
as ________.
Correct Answer Proving

True/False
Question Audio cassettes are the part of tools of training.
Correct Answer True

Match The Following
Question -Correct Answer
Current voltage -Multi meter
Speed -Tachometer
Running time- Stop watch
Temperature -Thermistors
Multiple Choice Multiple Answer
Question The price of the spare part depends on :-
Correct Answer Demand and supply position , Urgency of buyer ,
Level of negotiations


Multiple Choice Single Answer
Question What is more important while using components like nut
bolts, screws?
Correct Answer Standardization


Multiple Choice Single Answer
Question Maintenance spares are fast moving and are :-
Correct Answer Repetitive in nature


Multiple Choice Single Answer
Question With respect to Economy & with comparison to other
maintenance, Condition monitoring is :-
Correct Answer Costly


Select The Blank
Question Time required to diagnose is about ________ percent to total
down time.
Correct Answer 40-80


Multiple Choice Multiple Answer
Question Where CPM can be used?
Correct Answer In Construction Business , In Research & Development
Projects , Launching new products in Marketing


Select The Blank
Question Advanced & complex machinery is normally run at high speed
in order to give higher speeds of ________.
Correct Answer Production


Select The Blank
Question ________ charts prepared by the senior engineers of the
organisations for equipments in plant can be of great help.
Correct Answer Trouble shooting

No comments: